TM-5-5420-279-10
Replace Flatrack LVT
4.9.2.1
Strap down the launch equipment storage box to LVT flatrack ensuring that the R
clips have been inserted in the doors. Ensure all required loose items have been
removed for bridge building.
`R' CLIP
`R' CLIP
`R' CLIP
686A632
4.9.2.2
Reverse vehicle V3 with its left hand wheels along the left hand tire alignment line and
load flatrack LVT.
4.9.2.3
Return vehicle V3 and flatrack LVT to staging area and ground load flatrack LVT.
4.9.2.4
Transload flatrack T2 onto V2.
4.9.2.5
Drive vehicle V2 with flatrack T2 onto bridge site.
4.9.2.6
Reverse vehicle V2 with its left hand wheels on the left hand tire alignment line and
ground load flatrack T2 in line with V1 on the opposite side.