TM-5-5420-279-10
WARNING
CRUSH HAZARD. DEATH OR PERSONAL INJURY CAN RESULT IF THE CORRECT
PROCEDURE IS NOT FOLLOWED FOR ATTACHMENT OF THE BRIDGE MODULE LIFTER
TO THE PARALLEL MODULE.
5.4.3.15
Adjust the bridge module lifter to its middle setting and secure it in position with the
shootbolts.
5.4.3.16
Connect the bridge module lifter to the wire ropes located between the deck units on
the parallel module.
686A659
686A659b
686A659a
Sequence of Closing Bridge Module
5.4.3.17
Remove any debris or stones from the hinge lines of the parallel module.
5.4.3.18
Operate the lift and traverse controls on the crane. Using the tag lines, stack the
parallel module onto flatrack V2. Make sure the parallel module folds slowly and
progressively as it is lifted by the crane. Do not operate the traverse controls of the
crane until the module has fully closed.
5.4.3.19
Disconnect the bridge module lifter and the tag lines from the parallel module and
reconfigure the bridge module lifter to its widest setting.
5.4.3.20
Recover the four transportation aides from their stowed positions in the bridging
basket.
5.4.3.21
Fit four transportation aides to the parallel module, two per side, in between the deck
units as shown. The brackets being place between the deck units through which the
closing slings are accessed. The bracket is fitted with the white face up and facing
5-22