TM-5-5420-279-10
89
90
Stow the tail-lift.
91
Deploy the A-frame support struts and lower the A-frame.
92
Re-attach the articulator cylinders.
93
Reconfigure the launcher walkways for launch beam build configuration.
94
Raise the launch beam clear of the far bank.
95
Remove the launch beam final stop.
96
Manually raise the launch beam stop and reverse the launch beam.
97
Deploy the far bank approach ramps.
98
Deploy the curbs and bridge markers.
99
Strip out the launch beam.
100 Re-insert the launch beam final stop.
101 Stow all the walkways and ladders.
102 Fully retract the articulator cylinders.
103 Using the bridge lift function allow some slack in the bottom winch cable.
104 Stow the crane and the exhaust elbow.
105 Extend the A-frame stabilizers to their maximum height and pin.
106 Raise the tail-lift clear of the bridge and A-frame hydraulics.
107 Insert the relax mechanism shootbolts.
108 Turn the rotary switch in the cab to position 3.
109 Remove and stow the chest pack.
110 Reverse the launch vehicle to fully retract the slide frame.
111 Lower the A-frame onto chassis twist locks and fully retract the stabilizers.
112 Lock the twist locks.
113 Support the far bank support with the tail-lift.
114 Drive the launch vehicle clear of the bridge.
115 Deploy the home bank approach ramps.
116 Deploy the defile markers and road signs.
6-6