TM-5-5420-279-10
Manpower Requirements
6.1.1.1
Table 6.1 outlines the manpower required to
build a
40-meter bridge.
6.1.1.2
The manpower for construction of the bridge is drawn from the personnel required to
operate the bridge load transportation vehicles.
Man No.
Operator Name
Abbreviation
Vehicle
1
Chest Pack Operator
CPO
(LV) + LVT
2
Crane Operator
COP
3
Slinger 3/Top Man
SL3/TM
V1 + T1
4
Pin Man 1
PM1
5
Pin Man 2
PM2
V2 + T2
6
Pin Man 3
PM3
7
Slinger 1
SL1
V3 + T3
8
Slinger 2
SL2
Critical Task List
6.2.1.1
An analysis of the critical stages of building the 40-meter bridge follows.
6.2.1.2
The list should not be used to build the bridge as there is insufficient detail, but it may
be used by the bridge commander to keep track on the procedures while bridge build is
underway.
6.2.1.3
Should problems occur during the build sequence refer to Chapter 9 Bridge Build
Possible Mechanical Faults.
1
Position the vehicle on the centerline.
2
Apply the parking brake and place the transmission in neutral.
3
Position and unstrap flatrack LVT on the build site.
4
Remove the mudguards.
5
6
Unstrap the tail-lift.
7
Connect the tail-lift pendant.