ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
CHAPTER 7
LINK REINFORCED BRIDGES
Page
Section I.
GENERAL....................................................................................................................... 7-1
Section II.
NORMAL SITES ............................................................................................................. 7-14
7-1
ASSEMBLY 2E + 22 BAY- LINK REINFORCED............................................................ 7-14
7-2
DISASSEMBLY - 2E + 22 BAY LINK REINFORCED..................................................... 7-25
7-3
DISASSEMBLY ON ORIGINAL FAR BANK................................................................... 7-34
Section III.
COUNTERWEIGHTS - LINK REINFORCED BRIDGES ................................................ 7-38
7-4
2E + 19 BAY - NORMAL SITE........................................................................................ 7-38
7-5
2E + 20 BAY - NORMAL SITE........................................................................................ 7-38
7-6
2E + 21 BAY - NORMAL SITE........................................................................................ 7-38
7-7
2E + 22 BAY - NORMAL SITE........................................................................................ 7-39
Section IV.
ANCHORAGE - LINK REINFORCED BRIDGES ........................................................... 7-40
Section I. GENERAL
a.
Introduction. The construction (assembly) and delaunch (disassembly) of link reinforced bridges is described
in step by step procedures in this chapter.
The assembly procedures start with the setting up and alignment of the roller beam, followed by step by step
assembly instructions to construct the bridge. Similarly, disassembly procedures contain full step by step instructions.
Disassembly is not the exact reverse of assembly; there are differences, therefore the step by step procedures shall be
followed carefully. These procedures are covered in more detail in Chapter 4 General Drills. The operator should be
familiar with these drills before following the step by step procedures in this chapter.
When familiarity is gained with the general drills and the step by step procedures, any link reinforced bridge up to
2E + 22 bay can be assembled using the Build and Boom Tables, and disassembled using the Delaunch Tables.
WARNING
Do not attempt to use the Tables until the general drills and step by step procedures have been
practiced a number of times.
7-1